Mechanical Memories Magazine

Issue: 2013-October - Issue 79

Dreamland
MARGATE
Save Dreamland Update October 2013
COURT OF APPEAL BACKS THE DREAMLAND TRUST AND
THANET DISTRICT COUNCIL
The owners' latest appeal was heard at the Court of Appeal on 25 th and 26 th
September. We are pleased to announce that the Court of Appeal has dismissed the
former owners' appeal against the High Court decision to uphold the confirmation of
the council's Compulsory Purchase Order.
PROJECT UP-DATE
On the 3 rd September the Dreamland site passed into the ownership of Thanet District
Council - a significant moment in Margate's history as Dreamland becomes the
Peoples' Park once again.
Community Pay Back young offenders were engaged to help clear the Dreamland car
park for re-opening and an eight-week survey programme is about to begin.
The design team were able to visit the site this month for the first time since their
appointment. Once the survey reports have been completed and the cost plan
reviewed, the project team will be able to finalise the plans and designs for lock down
and sign off.
Once the appeal decision has been released we will be opening the gates to Dreamland
and inviting all to join us in marking this milestone event - details will be released at a
later date.
Page4
MISLEADING MEDIA MESSES UP MESSAGES
The week of the appeal whipped up a real media frenzy. In this instance some of the
reporting was both misleading and unbalanced and so we must publicly put the record
straight!
BBC SE Inside Out programme broadcast on the 25 th September misled viewers into
believing that the £10m grant money secured for Dreamland, including Sea Change
and Heritage Lottery Funding, was to be used to purchase the Dreamland site - this, of
course, is not the case.
All secured grants are ringfenced for restoring the Grade II* listed Scenic Railway,
Grade II listed menagerie cages, front entrance to the park and bringing back into use
the internal cafe, event and retail spaces under the cinema building, ride restoration,
design, branding, content, landscaping, learning and training.
Site purchase costs are a separate matter and currently being negotiated between
Thanet District Council and MTCRC.
I'm so glad we' ve cleared that up- moving on! ....
BLACKPOOL MEETINGS
In September The Dreamland Trust had a series of meetings in Blackpool. This was an
opportunity to introduce Dreamland designers, Hemingway Design, to the Thompson
family who own and operate Blackpool Pleasure Beach, the park' s Head Engineer,
Steve Hughes and David Cam, Company Secretary and Director.
We also met with the Head of Blackpool Illuminations, Richard Ryan, who took us on
a tour of the illuminations depot at Lightworks.
And last week we played host, in Margate, to the Hastings Pier Trust. We look
forward to seeing the pier being restored over the next 18 months or so.
Page 5

Download Page 4: PDF File | Image

Download Page 5 PDF File | Image

Future scanning projects are planned by the International Arcade Museum Library (IAML).

Pro Tip: You can flip pages on the issue easily by using the left and right arrow keys on your keyboard.